AJ Project
Alaska, USA
- Client:
- Echo Bay Mines
- Years of Service:
- 1989 to 1994
- Project Description:
- The proposed AJ mine will be an underground gold mine with
an ore production of 22,500 tons per day.
Dr. Robertson was working with SRK when they were commissioned
to investigate the technical and
economic feasibility of six alternative tailings disposal sites, together
with alternative methods of dam construction. Studies showed that a
site on Sheep Creek approximately 4 miles southeast of Juneau offered
significant advantages over the other sites.
A roller compacted concrete (RCC) dam with a final height of 335 feet
was selected as providing the safest and most economical structure.
It will also allow staged construction over a 13 year period to reduce
initial costs. An inexpensive arrangement for a multi-level intake tower
and overflow spillway is provided. To preserve water quality in the lower
reaches of Sheep Creek, all excess water from the impoundment except
major floods will be discharged through a pipe to the ocean. The design
includes an option for using the same pipe as a penstock for a 5 MW
hydroelectric generating plant located near tidewater.
- Services Provided:
-
- Site selection, comparative assessment and site ranking of
potential tailings sites.
- Hydrology studies and evaluation of hydro-electric potential.
- Foundation investigations for RCC dam.
- Detailed design of RCC dam, spillway, intake structure and stilling basin.
- Development of detailed cost estimates.
- Preliminary routing of tailings and water reclaim pipelines.
| |