RGC Top Banner
 
red side bar

 
 
Home
 
Tools
 
Publications
 
Image Library
 
SOQ
 
Site Index
 
Search RGC website
 
Request for Services
 
RGC News
 
RGC Admin
 
FTP

 

EnviroMine

HydroMine

 
black side bar
RGC: Project Experience
Les Mines Selbaie
Quebec, Canada



Client:
Billiton Metal Canada Inc.

Years of Service:
1992

Project Description:
Les Mines Selbaie is a 7600 tonnes per day copper-zinc mill and mine which involves both underground and open pit workings. Copper and zinc flotation concentrates are shipped off-site for further processing. Other components of the mine site include overburden piles, mine rock piles, tailings impoundment and clarification pond. The mine rock has been segregated into highly acid generating, acid generating and non-acid generating piles. The initial tailings disposal system was based on the Robynski method of thickened tailings placed from a central discharge to form a cone. This system has been replaced by a conventional spigotted discharge and system of surrounding dykes. The clarification pond is used to settle fines from water draining from the tailings disposal system. Selbaie has been experiencing increasing acidic drainage from the mine rock piles, mine rock berms and tailings deposits. The acidity is controlled using a water treatment plant utilizing lime.

Services Provided:
Dr. Robertson was the Project Principal and Senior Technical Leader of the SRK team that was retained by Billiton to carry out a preliminary environmental liability evaluation followed by a more detailed environmental audit for the mine site as part of their pre- acquisition due diligence.

Environmental Liability Evaluation
A pre-acquisition site reconnaissance was conducted to assess current and potential issues of environmental liability. Inspections were made of the major mine and mill components, the property compliance data was reviewed and site personnel interviewed. These were non-sampling assessments, based on field observations and technical review of the main components at the site. Consequently, the liability assessments and cost estimates relied, to a large extent, on our experience and engineering judgement. Closure plan options were developed to address the major issues, with an estimate of the costs for implementation of the recommended options.

Environmental Audit
The objective of this phase was to complete the detailed site environmental audit. Where possible, this phase of data gathering and evaluation followed work previously done on site. There were components of the audit pertaining to acid rock drainage and mine environmental liability and costs that had not been identified previously. In assessing financial liability, compliance under current permit or regulatory requirements was assessed and also the additional environmental liability considered likely in the near future (less than 10 years) under the prevailing regulatory trends.

red side bar black side bar  
Developed and Maintained by Robertson GeoConsultants Inc.
Suite 330, 580 Hornby Street, Vancouver BC, CANADA V6C 3B6
Tel: (604) 684-8072 Fax: (604) 684-8073 e-mail: rgc@infomine.com 
  Top Menu Bar by: Milonic Solutions Ltd.   ;   Other Links
copyright © 2000-2008 Robertson GeoConsultants Inc.